1.0 OBJECTIVE:
1.1 To lay down a procedure for Maintenance of Manufacturing Plant.
2.0 SCOPE:
2.1 This procedure is applicable for manufacturing plant.
3.0 RESPONSIBILITY:
3.1 The concerned Technician shall carry out the Preventive maintenance Procedure.
3.2 The Officer Engineering should be responsible for implementation of Preventive maintenance Procedure.
3.3 Head of Engineering Department will be responsible for compliance of Preventive Maintenance Procedure.
4.0 ABBREVIATIONS
4.1 MCC : Machine Control Centre
To read this SOP click here SOP for Operating And Cleaning Procedure For Automatic Liquid Bottle Filling Machine.
5.0 PROCEDURE:
5.1 Switch Off the Power Supply from MCC.
5.2 Check and tighten the foundation bolts of the Manufacturing Plant
5.3 Check the gearbox drive motor.
5.4 Check the oil level in gear box.
5.5 Check the rotation of main impeller.
5.6 Greasing of the Main Column of the manufacturing plant.
5.7 Check lid opening and closing.
5.8 Check the hydraulic oil level in hydraulic power pack and top up oil if required.
5.9 Check and tighten all electrical connection of the Manufacturing Plant Vessels.
5.10 Check the straightness of the shaft of the oil Phase and Water phase vessel.
5.11 Check the transfer pump for any abnormal sound and leakages.
5.12 Check the leakages in the pipes and found then tighten the gasket & clamp.
5.13 Check for any steam leakages & tighten if required.
5.14 Check for proper operation of the steam solenoid coil. Replace if required.
5.15 Clean the Electrical panel by blower and tighten all electrical connection.
5.16 Check the condition of the Mechanical seal in the homogenizer. Replace if required.
5.17 Record the observation on Maintenance checklist.